Battery failure causes 60% of all UPS system failures. The only way to know whether your batteries will perform during a real outage is to test them. Sukhai UPS provides professional impedance testing, discharge load testing, thermal imaging, and float voltage verification for VRLA, SMF, and tubular battery banks — predicting failure before it happens and giving you time to plan a replacement.
The UPS battery bank is the most failure-prone component in your power protection system. Industry data consistently shows that battery-related faults account for approximately 60% of all UPS failures. Yet unlike other UPS components that signal their failure with alarms, most VRLA battery cells fail silently — the UPS display continues to show "Battery OK" right up until the moment mains power fails and the battery system collapses.
The consequences of untested battery failure during a real outage are significant. In a data centre, a silent battery failure means the UPS cannot provide the runtime needed to safely shut down servers or transfer to a generator — resulting in unplanned server shutdowns and potential data corruption. In a hospital, it may mean life support and monitoring equipment loses power. In a bank, it means core banking servers go down during peak transactions.
The good news is that VRLA battery degradation follows a predictable pattern that can be detected months in advance using the right testing methods. Impedance testing identifies cells with elevated internal resistance that are losing capacity. Discharge load testing measures actual runtime against rated specifications. Thermal imaging detects abnormal heat signatures from cells under stress. Together, these tests provide a comprehensive picture of battery health and give you months — not hours — of warning before a failure.
At Sukhai UPS, we have been testing and assessing UPS battery banks since 1999. Our engineers are trained on all major battery testing methodologies and carry calibrated test equipment for on-site testing at your facility.
Our battery testing services cover all major test methodologies used in the UPS industry. Tests are performed on-site at your facility with no need to take your UPS offline.
The most widely used battery health screening method. A small AC signal is applied to each cell and the resulting impedance (internal resistance) measured in milliohms. Healthy VRLA cells show low, consistent impedance values. Cells showing impedance 25% or more above baseline are degraded. Non-invasive — the UPS remains live throughout.
The most definitive battery health test. The UPS is switched to battery mode under a controlled test load, and actual runtime is measured until the batteries reach end-of-discharge voltage. Results are compared against rated specifications at that load level. Batteries delivering less than 80% of rated runtime should be replaced.
Float charging voltage is measured per string and per block while the UPS is on mains power. Incorrect float voltage — either too high (overcharging) or too low (undercharging) — accelerates battery degradation. Charger set points are adjusted if readings are outside the manufacturer's range, with no load disruption.
Infrared thermography scan of battery strings, intercell connections, and racks. Hot spots in a battery string indicate cells running at elevated temperature — a sign of elevated internal resistance, thermal runaway risk, or high discharge current. Thermal images captured and included in the test report.
Physical inspection of all batteries, intercell links, terminal connections, racks, and cabinets for signs of electrolyte leakage, case bulging, terminal corrosion, cracks, and mechanical damage. Visual inspection complements electrical testing and identifies physical failure modes that electrical tests may not detect.
Our testing process is structured, documented, and designed to cause zero disruption to your operations during non-invasive tests.
Prior to the test visit, we confirm the UPS model, battery configuration, number of strings, and any planned maintenance windows needed for discharge testing. We ensure the batteries have been on float charge for a minimum of 24 hours before impedance testing.
Impedance and thermal tests are performed with the UPS live and load connected — zero disruption to your operation. Discharge tests are performed during a planned maintenance window. Each battery cell is individually tested and recorded using calibrated instruments with traceable standards.
Test results are compared against manufacturer baseline values, historical readings (if previous tests were conducted), and industry standard thresholds (IEEE 1188 / 450). Each battery is graded: Green (healthy), Amber (monitor), or Red (replace).
A comprehensive written test report is provided within 24 hours of the visit. The report includes all measurement data per cell, thermal images, graded findings, and prioritised recommendations with an estimated replacement timeline.
Timing your battery tests correctly maximises the value of the testing programme and ensures you are never caught off-guard by battery degradation.
For battery banks less than 2 years old, annual impedance testing establishes a baseline against which all future tests will be compared. This baseline is as important as the first test result — without it, you cannot measure the rate of degradation over time.
VRLA battery degradation accelerates after 2 years in Indian ambient temperature conditions (25–35°C). Semi-annual testing from year 2 onwards provides earlier warning of the accelerating degradation phase.
For hospitals, data centres, and banking systems where any battery failure has serious consequences, quarterly impedance testing combined with an annual discharge test provides the highest level of confidence in battery health.
India's monsoon season brings increased incidence of power outages. Testing battery banks in April–May — before the monsoon — ensures your batteries are confirmed healthy and capable of delivering rated runtime before the highest-demand period of the year.
Many ISO, data centre, and banking regulatory audits require evidence of UPS battery health testing. A battery test report from Sukhai UPS, clearly showing test methodology, results, and recommendations, satisfies this requirement.
If your UPS batteries have been fully discharged — due to a prolonged outage or accidental deep discharge — a battery test should be conducted after recharge to verify that no cells were permanently damaged by the deep discharge cycle.
When our battery testing reveals poor health, Sukhai UPS can supply and install replacement batteries immediately, minimising the window between discovery and correction.
If testing reveals batteries that need immediate replacement, we supply genuine OEM replacement batteries from Exide, Amara Raja Quanta, Amaron, and Leoch SMF batteries. Same-day or next-day replacement is available for critical customers. View our battery replacement service.
The key benefit of regular battery testing is converting battery replacement from an emergency reactive event into a planned, budgeted activity. When testing gives you 6 to 12 months of warning, you can obtain quotes, approve budgets, and schedule replacement at a convenient time — rather than reacting to a midnight failure.
Our UPS AMC plans include battery impedance testing at every quarterly PM visit. This means batteries are tested four times per year as part of normal maintenance — the most cost-effective way to implement a comprehensive battery health programme.
Battery testing included in every quarterly PM visit under AMC. The most cost-effective way to run a comprehensive battery health programme for your UPS fleet.
View AMC Services →Standalone PM visits include battery impedance testing, thermal imaging, and visual inspection as standard. See our full PM checklist and scheduling options.
View PM Services →Test results showing degraded batteries? We supply and install Exide, Quanta, Amaron, and Leoch replacement batteries with same-day response for critical systems.
View Battery Replacement →Also see: SMF Batteries | Exide Batteries | Quanta Batteries | 3-Phase UPS | UPS AMC Services